Hawks I / II, Japan

Size: 13 MWp  Grid Connection: 2017, 2018  Role: Development, EPC, Financing, Investment

Size: 13 MWp

Grid Connection: 2017, 2018

Role: Development, EPC, Financing, Investment

Date, Japan

Size: 10.3 MWp  Grid Connection: 2017  Role: Development, EPC, Financing, Investment

Size: 10.3 MWp

Grid Connection: 2017

Role: Development, EPC, Financing, Investment

 

Kawasaki, Japan

Size: 19.8 MWp  Grid Connection: 2015  Role: Development, EPC, Financing, Investment

Size: 19.8 MWp

Grid Connection: 2015

Role: Development, EPC, Financing, Investment

Shirakawa I / II, Japan

Size: 18.8 MWp  Grid Connection: 2014  Role: EPC

Size: 18.8 MWp

Grid Connection: 2014

Role: EPC

 

Wahlsdorf, Uthleben & Zagelsdorf, Germany

Size: 22.4 MWp (Wind)  Grid Connection: 2014-2016  Role: Co-Development, EPC, Financing and Investment in 3 wind parks

Size: 22.4 MWp (Wind)

Grid Connection: 2014-2016

Role: Co-Development, EPC, Financing and Investment in 3 wind parks

Neudietendorf, Germany

Size: 5.6 MWp  Grid Connection: 2013  Role: EPC, Financing, Investment

Size: 5.6 MWp

Grid Connection: 2013

Role: EPC, Financing, Investment

 

Müssentin, Germany

Size: 6.4 MWp  Grid Connection: 2012  Role: EPC, Financing, Investment

Size: 6.4 MWp

Grid Connection: 2012

Role: EPC, Financing, Investment

Schwarzheide, Germany

Size: 10 MWp  Grid Connection: 2012  Role: EPC, Financing, Investment

Size: 10 MWp

Grid Connection: 2012

Role: EPC, Financing, Investment

 

Kremmen, Germany

Size: 7 MWp  Grid Connection: 2012  Role: Development, EPC, Financing, Investment

Size: 7 MWp

Grid Connection: 2012

Role: Development, EPC, Financing, Investment

Dallgow, Germany

Size: 21 MWp  Grid Connection: 2012  Role: Development, EPC, Financing, Investment

Size: 21 MWp

Grid Connection: 2012

Role: Development, EPC, Financing, Investment

 

Senftenberg, Germany

Size: 82 MWp  Grid Connection: 2011  Role: Co-Development

Size: 82 MWp

Grid Connection: 2011

Role: Co-Development

Zerbst, Germany

Size: 45 MWp  Grid Connection: 2011  Role: Development

Size: 45 MWp

Grid Connection: 2011

Role: Development

 

Briest, Germany

Size: 90 MWp  Grid Connection: 2011  Role: Development

Size: 90 MWp

Grid Connection: 2011

Role: Development

Finsterwalde, Germany

Size: 80 MWp  Grid Connection: 2010  Role: Co-Development, EPC and Financing Support

Size: 80 MWp

Grid Connection: 2010

Role: Co-Development, EPC and Financing Support